Constructive acceleration claim: what must the contractor prove, and what does the scheduling expert have to show?

Constructive acceleration is the claim a contractor brings when the owner refuses a time extension the contractor is owed and still holds it to the original completion date. On federal contracts the Federal Circuit and the ASBCA require five elements, beginning with an excusable delay on the critical path. In the three federal decisions below, the contractors lost on the excusable delay or on the request for an extension.

A contractor from behind watches a late crew, a rolled schedule under one arm.

What is constructive acceleration?

A claim that the owner, by refusing a time extension the contractor was owed and holding it to the original completion date, in effect ordered faster work. The contractor recovers the cost of the added resources as a change.

In Fraser Construction Co. v. United States, 384 F.3d 1354 (Fed. Cir. 2004), Judge Bryson wrote for the court that the claim "ordinarily arises when the government requires the contractor to adhere to the original performance deadline set forth in the contract" even though the contractor has met an excusable delay. The Armed Services Board of Contract Appeals (ASBCA) put it in one line in Appeal of Skanska USA Building, Inc., ASBCA No. 62430 (Sept. 23, 2021): "Constructive acceleration occurs when the government demands compliance with an original contract deadline."

Acceleration can also be ordered openly. Paragraph (a) of the FAR Changes clause, 52.243-4 (June 2007), lets the contracting officer issue a written change order that accelerates performance. Paragraph (b) covers everything else: any other written or oral direction, instruction, interpretation or determination of the contracting officer that causes a change is treated as a change order, provided the contractor gives the written notice the clause describes.

The elements below come from federal decisions, the Federal Circuit and the ASBCA, on government contracts. Private and state contracts are decided under their own terms and state law.

What are the five elements of a constructive acceleration claim?

An excusable delay, a timely and sufficient request for an extension, a denial or no action within a reasonable time, the owner's insistence on the shorter schedule, and extra resources spent to stay on it.

The ASBCA listed them in Skanska. The contractor must prove "that the contractor encountered a delay that is excusable under the contract;" "that the contractor made a timely and sufficient request for an extension of the contract schedule;" and "that the government denied the contractor's request for an extension or failed to act on it within a reasonable time."

The fourth element is that the government insisted on completion within a period shorter than the period to which the contractor would be entitled with an extension, and that the contractor notified the government that it regarded the alleged order to accelerate as a constructive change. The fifth is "that the contractor was required to expend extra resources to compensate for the lost time and remain on schedule."

The Federal Circuit used the same list in Amatea/Grimberg JV v. Secretary of the Navy, No. 2024-1006 (June 25, 2025), a nonprecedential opinion by Judge Hughes: "The five elements of constructive acceleration are: (1) the contractor encountered an excusable delay;" and the court went on through the request, the denial, the insistence and the added expense. All five are required, so a claim that fails on one element fails as a whole.

What counts as an excusable delay?

A delay from causes the contractor could not foresee or control and that were not its fault or negligence, as FAR 52.249-10 defines it. The Federal Circuit adds that the cause must delay the critical path.

Paragraph (b)(1) of the Default clause for fixed-price construction, FAR 52.249-10 (April 1984), protects the contractor if "The delay in completing the work arises from unforeseeable causes beyond the control" and without the fault or negligence of the contractor. The clause gives examples: acts of the government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of subcontractors or suppliers that meet the same test.

Paragraph (b)(2) adds a notice condition. The contractor, "within 10 days from the beginning of any delay (unless extended by the Contracting Officer)," notifies the contracting officer in writing of the causes of delay. The contracting officer then finds the facts, decides the extent of the delay and may extend the time for completion.

In Amatea/Grimberg the court quoted the same definition and added a condition taken from scheduling: "The unforeseeable cause must also affect the "critical path of performance," delaying contract completion." An event that slows work with float left in it does not delay completion, and an acceleration claim built on it fails on the first element.

What happened in Amatea/Grimberg JV v. Secretary of the Navy?

The Federal Circuit affirmed the denial of the claim in 2025. The extra work the Navy demanded on security and sprinkler systems did not delay completion, and the contractor had no expert to answer the Navy's critical path analysis.

The contract was for an energetics system and technology laboratory complex at the Naval Surface Warfare Center in Indian Head, Maryland. The Navy issued the solicitation in July 2009 and awarded the contract to the joint venture in September 2009. The original completion date was March 31, 2011, the extended date March 29, 2012, and the building was ready for beneficial occupancy on September 29, 2012. Liquidated damages ran at $5,250 per calendar day.

The joint venture said the Navy demanded additional work on the electronic security system and the fire sprinklers without extending the schedule or allowing night or weekend work, and that its subcontractors worked overtime and added resources after its request for more time was denied. It also claimed that the denial of its requests to work outside regular hours, including every Saturday, breached the contract.

The ASBCA, in nine consolidated appeals before Administrative Judges Prouty, Witwer and Shackleford, found that "there has been zero evidence presented by AGJV that work on the ESS or the fire sprinklers caused a delay" to completion. The Federal Circuit noted that the joint venture "did not provide its own expert to contest the Navy's expert's critical path analysis." The court affirmed the denial of both claims and found that the Board applied the correct legal standards and that substantial evidence supported its findings.

Does a time extension or a release of liquidated damages prove that the delay was excusable?

No. In Amatea/Grimberg the Navy had extended the completion date and released part of the liquidated damages, and the Federal Circuit refused to treat either step as proof that the government caused the delay.

The Navy assessed liquidated damages for the period between March 29 and September 29, 2012 and later released part of them. The joint venture argued that the extension and the release showed excusable delay. The court answered: "We have clearly rejected a presumption that the government is at fault for delay" when a contracting officer grants a time extension.

After an extension or a release, the contractor still proves, event by event, that the delay was excusable and that it reached the critical path. In Amatea/Grimberg that proof was missing: the joint venture had no critical path analysis of its own.

Must the contractor request a specific extension?

Yes. In Skanska the ASBCA granted the government summary judgment on acceleration because Skanska reserved its rights and promised to quantify the impact later, but never asked for a specific extension before it accelerated.

The project was the Asymmetric Warfare Group Headquarters Complex at Fort Meade, Maryland. The U.S. Army Corps of Engineers awarded fixed-price Contract No. W912DR-13-C-0002 to Skanska on October 30, 2012, for $30,761,850. The contracting officer had 30 calendar days to review shop drawings. After the steel subcontractor found design discrepancies, the government revised the steel design and delivered final drawings on April 24, 2013, and the steel delay pushed the critical path.

Skanska sent the shop drawings in 12 sequences, received between June 12 and June 21, 2013. The government missed the 30-day review window for several of them, and Skanska later reported ten submittals 15 to 29 days overdue, some with missing sheets. On July 15 and August 2 Skanska wrote that it reserved its rights to recover all costs of the delay "once the full impact is realized," and on August 12 that it would seek reimbursement for all costs of the delay. On August 27, 2013, Modification A00005 extended completion by 90 calendar days and increased the price.

Between October 17 and November 1, 2013 Skanska emailed its subcontractor Steel Fab about weekend work and more manpower, and the government was not part of these emails; the Board found these emails were the only evidence of a demand to accelerate. Skanska's change order request of November 27, 2013 sought added staff, overtime and construction costs but no additional days, and Modification A00023 of June 11, 2014 added $200,214 and 20 days. On July 2, 2019 Skanska filed a certified claim of $428,774 for its subcontractors Central Penn and Steel Fab, and the contracting officer's final decision denying it was received on December 6, 2019.

Administrative Judge Laura Eyester wrote that the doctrine "requires that the government be afforded an opportunity to grant or deny a time extension." Skanska "has offered nothing to show, or even hint, that it requested a specific time extension" before accelerating, so there was nothing for the government to deny. The government's motion did not seek dismissal of Skanska's separate claim for delay damages, and that claim stayed before the Board.

When does the owner's pressure become an order to accelerate?

When concern about progress comes together with a refusal to extend time after the contractor has raised a valid claim for more time. A mere failure to grant an extension at the time is not an order to accelerate.

Fraser arose on a flood control project of the Army Corps of Engineers on the South Fork Zumbro River in Rochester, Minnesota. Fraser Construction Company had a contract for $744,585 to excavate the lakebed of Silver Lake. In the summer of 1993 high water repeatedly overtopped Fraser's diversion dike and flooded the site. Fraser said the Corps's refusal to grant adequate time extensions forced it to keep working and claimed $659,760 beyond the contract price.

The court wrote that "an expression of concern about progress, combined with a refusal to issue extensions" can amount to an order to accelerate, but not always, "particularly if the expression comes before the time when the contractor has raised a specific and valid claim." The Corps's letter of June 28, 1993 was sent before Fraser first claimed excusable delay from high flows, and the court found it "not unreasonable for the Corps to remind Fraser of its responsibility to adhere to its contract schedule." The letter of July 15 "did not suggest that Fraser was required to work regardless of whether it was entitled to an extension." The court also wrote that "[M]ere failure to grant an extension at the time will not constitute a constructive order to accelerate."

Fraser lost on entitlement to time: "Fraser has failed to prove that it was entitled to an additional period for performance under the contract." It did not show that it was entitled to suspend operations for the whole summer, and it did not identify particular days for which it had made valid extension requests that were denied. The Federal Circuit affirmed the judgment of the Court of Federal Claims.

Refusals of extra working hours are judged by the same yardstick of reasonableness. In Amatea/Grimberg the court held that "the CO's denial of AGJV's requests for extended hours was not arbitrary." A general claim of being behind schedule was no justification for the requests, and the Navy had approved part of them, extended weekday hours and three Saturdays.

What notices does a federal construction contractor have to give?

Three: written notice of the causes of delay within 10 days under FAR 52.249-10, a request for a specific extension, and notice under FAR 52.243-4(b) that the contractor regards the order to accelerate as a change.

Under paragraph (b) of the Changes clause the notice states the date, circumstances and source of the order and that the contractor regards it as a change order. Paragraph (c) closes the door on everything else: except as the clause provides, "no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause."

Paragraph (d) limits the money. For a change under paragraph (b), no adjustment covers costs incurred "more than 20 days before the Contractor gives written notice," with an exception for defective specifications. Under paragraph (e) the contractor asserts its right to an adjustment within 30 days after giving that notice, unless the government extends the period, and paragraph (f) bars proposals asserted after final payment.

In Skanska the letters reserved rights and announced a claim for costs, but none requested a specific number of days, and the Board decided the acceleration claim on that ground. The expert who later prices the acceleration works within these dates: overtime and added crews paid more than 20 days before the written notice are outside a paragraph (b) adjustment.

What does the scheduling expert have to show?

That the excusable event delayed the critical path, by how many days, which days were requested and refused, and that added crews, shifts or overtime recovered that time. A cost expert prices those resources.

The schedule analysis carries the first element. The expert works from the baseline schedule and its updates, places each event on the activities it touched and measures the effect on the completion date. In Amatea/Grimberg the Navy had such an analysis and the contractor had none, and the Board found no evidence that the disputed work delayed completion.

The same analysis has to line up with the paper trail. Fraser lost in part because it did not identify particular days with valid extension requests that were denied, and Skanska because it never asked for days before it accelerated. An expert report that matches each day of excusable delay to a request, a refusal or silence, and the order or pressure that followed, answers the second, third and fourth elements together.

The fifth element is a cost question. The cost expert separates the premium portion of overtime, added shifts, extra crews and equipment brought in to recover time from the costs the contractor would have incurred anyway, and checks the dates against the 20-day limit of FAR 52.243-4(d). Where the claim also seeks lost productivity from overtime or crowding, that part needs its own proof from project data.

How does IAE find an expert for a constructive acceleration claim?

In the request choose the case type Construction and describe the project, the delay events, the extension requests and the forum. Within 5 business days IAE sends 2-3 candidates with CVs, hourly rates and lists of prior testimony.

The IAE page on construction expert witnesses lists 7 specialties: structural engineering, geotechnical engineering, architecture, building envelope, MEP systems, cost estimating and scheduling. On that page scheduling experts analyze delay, cost estimators price the scope the engineers define, and home office overhead for delay on a federal contract is computed with the Eichleay formula. The page notes that state courts apply their own rules on expert admissibility, so the request names the state and the court, or the board.

The request form asks for the field of expertise, the case type, the state and court, the firm's side, the expert disclosure deadline, the parties and their counsel for the conflict check, and a short description of the case. The form asks not to include privileged or sealed information. Within 1 business day IAE replies whether it can search in that field by the deadline.

The search costs $2,000 per case, paid in advance, and candidate names and CVs come after payment. Each candidate confirms in writing that he or she has no ties to the parties or their counsel. The candidate materials include testimony in the last 4 years and publications in the last 10 years. If no candidate fits, the second search is free; if IAE finds no candidates, it refunds the fee. IAE is not a law firm: the notices, the extension requests and the claim stay with the contractor's or the owner's counsel.

Sources

Read also

All articles

Expert witnesses

Need an expert witness for your case?

Describe the question, the case type and the court. Within 5 business days you receive 2-3 candidates with CVs, hourly rates and lists of prior testimony.

Expert request

Received

Candidates, rates and prior testimony within 5 business days

Candidates2-3 with CVs
Timeline5 business days
Search$2,000 per case