Measured mile analysis: how is lost labor productivity proved in a construction claim?
A measured mile analysis prices lost labor productivity by comparing the contractor's own output in a period or area the disruption did not touch with its output where the disruption hit. The Armed Services Board of Contract Appeals calls this good period versus bad period comparison a well established method of proving damages. Claims stand or fall on the baseline, on causation and on the records behind both.

What is a measured mile analysis?
A comparison of the contractor's labor productivity in a period or area the disruption did not touch with its productivity where the disruption hit. The difference, applied to the affected work, prices the inefficiency.
The Armed Services Board of Contract Appeals (ASBCA) describes the approach in Appeal of King Aerospace, Inc., ASBCA No. 60933, decided on April 15, 2019, as a comparison of the productivity of an impacted period of the project with the productivity of an unimpacted period. The concurring opinion cites United States Industries, Inc. v. Blake Construction Co., 671 F.2d 539 (D.C. Cir. 1982), as the leading case.
In Appeal of Perini Corp., ASBCA No. 51573, decided on May 12, 2004, the Board traced the method to DANAC, Inc., ASBCA No. 33394, which treats a "good period vs. bad period" analysis of labor inefficiency as "a well established method of proving damages." Perini's brief never used the words measured mile, yet the Board found that its formula "is an application of the 'measured mile methodology.'"
The arithmetic is short. The unit rate the crews achieved in the baseline is applied to the quantity installed in the impacted period, and the labor hours actually spent above that figure are the claimed loss. Everything else in a dispute over a measured mile concerns the inputs: which period counts as unimpacted, whether the work in both periods is comparable, and which part of the loss the other party caused.
Why do courts prefer it to industry productivity tables?
Because it uses data from the project itself. In Trane US Inc. v. Yearout Service, LLC (M.D. Ga. 2019), the court excluded an expert who applied trade association tables to payroll records instead of measuring the job.
Judge Marc T. Treadwell signed the order on June 20, 2019. The project was a design-build hangar renovation at Robins Air Force Base in Georgia. GSC Construction, Inc. was the general contractor, Allied World Specialty Insurance Company its surety, and Yearout Service, LLC the subcontractor that provided a "turnkey mechanical and plumbing system." Yearout's expert, Randy Lynn, put overtime inefficiency at $281,481.96 with markups, on a base of $202,388.00, and shift-work inefficiency at $50,390.59, on a base of $35,670.93.
For overtime, Lynn estimated the loss "simply by using payroll records" and applied percentages from Bulletin OT1 of the Mechanical Contractors Association of America (MCAA). The court found that the four studies behind the bulletin were thinly described, were not in the record and had not been read by Lynn. The bulletin itself says that overtime "can result in a substantial loss of labor productivity," not that it always does. Lynn also counted overtime weeks that were not consecutive as if they were, although the MCAA says a return to a 40-hour schedule can reset productivity.
For shift work, Bulletin OT2 "simply describes different ways in which shift work can impact labor efficiency," and the court added: "Nowhere in that bulletin is there any data, merely speculation." Lynn assigned a 10% loss to the first shift and 20% to the second. Asked where the percentages came from, he said they came "from my experience."
Against this the court set the measured mile, a method that "uses actual facts and data from a project." Lynn acknowledged that the method exists but did not use it, and he did not visit the job site or ask about actual conditions there. The court granted the motion of GSC and Allied World to exclude Lynn's testimony and wrote that it "does not pass muster under Daubert." It added that it did not question his qualifications.
How is the unimpacted period chosen?
From work that the disputed events touched far less than the claim period. In Perini the Board used 1992-93 as the baseline in place of 1991, because two government changes had affected 1991 performance.
Perini's contract with the Department of State, No. S-54-FA-237, covered work in Caracas, Venezuela, including temporary facilities, earthwork and rock fill. The price as last amended was $37,226,737.
In 1991 the rock fill changes had brought 153 days of time extensions under Modifications 10 and 11, and a rock mass reinforcement change had caused 56 days of delay. The years 1992-93 were affected by "far fewer changes and delays," and the Board agreed that they, and not 1991, set the baseline. A baseline taken from a period that already carries the other party's disruption understates the loss, and one taken from the easiest work on the job overstates it.
King Aerospace concerned an Army contract, No. W58RGZ-05-C-0302, for aircraft maintenance and repair. Performance began on September 1, 2005, and the Board had found entitlement in an earlier decision, ASBCA No. 57057, on claims about the condition of the aircraft and the parts, drawings and records the government furnished. King's expert, Donald Lochabay, used a modified measured mile. For labor he compared maintenance hours per prior-year flight hour in the bad years with a 2012-2013 baseline. For parts and materials he used a 2009-2012 baseline, and he capped the labor figure at the total-cost amount.
The government's expert, Timothy Overman, agreed that a measured mile was the right tool. He found labor impacts only in 2009, 2010 and 2011 and no basis for damages on parts and materials, where only one year exceeded the pre-bid estimates and the trends were "all over the place." The two experts therefore disagreed less about the method than about which years belonged on each side of the comparison.
Can the baseline come from a different project?
In some courts, yes. According to the law firm Bradley, a federal court in Colorado in 2023 admitted a measured mile that compared two projects, because the expert showed the work was reasonably similar and explained the differences.
The case is Agri-Systems v. Structural Technologies, LLC, No. 1:19-cv-02238 (D. Colo.), a diversity suit for breach of contract filed on August 7, 2019. The docket lists Filing 124, an order of Senior Judge Christine M. Arguello signed on May 16, 2023, which denied three motions in limine: Filing 92 to disqualify Matthew Hamlin or preclude his testimony, Filing 93 to exclude the testimony of Steven Bjordahl, and Filing 94 to exclude the testimony of Matthew Blackmer or disqualify him.
Bradley's summary of the order says the defendant attacked the plaintiff's measured mile because it compared work on different projects. The court rejected the idea that a reliable measured mile must come from the same project and required that the impacted and unimpacted work be "reasonably similar." The expert had listed the differences between the projects, among them location, crew and equipment size and the type of reinforcing, and explained why they did not defeat the comparison.
In Bradley's account the court also found that the choice of baseline was not "arbitrary or chosen to achieve a predetermined result," and held that differences the expert left unexplained "would go to the weight given to the testimony and not its admissibility." The docket page shows only the text of the docket entry, and the quotations in this section are taken from the Bradley article by John Mark Goodman of June 20, 2023.
Must the other party have caused every loss in the bad period?
No, but the contractor proves which part it did cause. Perini held that bad-period delays need not be entirely the government's fault, while King Aerospace placed the burden of proving government-caused costs on the contractor.
In Perini the Board read DANAC this way: it "does not require that 'bad period' delays be entirely the fault of the government." The government had argued that the Board never found all of the 1991 productivity losses to be its fault, and the Board did not adopt that position when it ruled on the baseline.
In King Aerospace the Board stated the other half of the rule. Citing Servidone Construction Corp. v. United States, 931 F.2d 860 (Fed. Cir. 1991), the majority opinion of Administrative Judge McIlmail held that King had to prove the government caused its increased costs. It called King's estimate unconvincing because King asked the Board to infer from fluctuations in labor hours that the aircraft and inventory conditions caused most of its labor costs at the El Paso site.
The concurrence of Judges Prouty and Shackleford agreed that "the burden of proof is on King to prove its damages." In Trane Lynn relied on the fact that Yearout's workers needed more man-hours than Yearout's management had estimated, and the court answered that "there are myriad reasons a worker could work slowly." An expert who builds a measured mile therefore separates, in the bad period, the hours lost because of the other party's events and the hours lost because of the contractor's own problems, weather, learning curve or bid errors.
What happens if the comparison does not measure productivity?
The board may reject it and adopt the other side's figure. In King Aerospace the majority wrote that King's measured mile did not measure productivity and awarded the government expert's labor figure of $3,640,794.
The majority's sentence was short: "King's 'measured mile' does not measure productivity." The opinion also faulted King for not tracking its actual costs as the work went on and for not reviewing the work cards, which it could have done.
The concurrence disagreed with much of that analysis. It concluded "that Mr. Lochabay utilized an acceptable measured mile methodology" and treated productivity as a stand-in for how much more costly performance became. It still rejected parts of his numbers, writing that the measured mile analysis, "like any damages model, must be grounded upon reality." Lochabay had conceded that his metric was not strictly productivity.
The money followed the government's expert. King's certified claim of $22.6 million reached the contracting officer on August 10, 2009. At the quantum hearing King sought $6,418,176 for aircraft condition and $2,054,297 for the parts inventory, plus $191,574 for preparing its request for equitable adjustment. Overman adopted Lochabay's labor figures for 2009, 2010 and 2011, which came to $3,640,794 with overhead. The Board sustained the appeal in the amount of $3,832,368, that figure plus the preparation costs, with interest under 41 U.S.C. 7109 from August 10, 2009, and denied the rest.
Can the same comparison measure delay?
Yes. In Perini the Board used the progress rate of the baseline years to compute how long the remaining work should have taken, and the result cut the liquidated damages the government had assessed.
Work performed by December 31, 1991 was worth $5,538,232, or 16% of the contract. By December 31, 1993 the figure was $31,253,019, or 83.78%. The 1992-93 work came to $25,714,787, or 67.78%, and the Board corrected the 82% progress for those years in Perini's formula. Over 731 days that work gave a daily rate of $35,177.55. At that rate the unperformed balance of $5,973,718 at the end of 1993 needed about 170 days.
The Board found 374 days of excusable delay for 1994-95, where its earlier decision had found 340, and raised total excusable delay to 422 days; the January 30, 2004 decision had allowed 366. Enforceable liquidated damages fell to 22 days out of the 444 the government had assessed. At $5,500 a day the reduction was $2,321,000. Perini remained liable for $286,000 in liquidated damages and penalties, $5,500 and $7,500 a day for 22 days, instead of the $2,892,000 the government had assessed.
Which records does a measured mile need?
Labor hours recorded by activity as the work went on, quantities installed in the same periods, and records of the events that caused the disruption. Payroll totals and published tables did not carry the analysis in Trane.
The comparison is only as good as the cost coding. Hours booked to one general code cannot be split later into the activity affected by the disruption and the activity that was not. In King Aerospace the Board noted both gaps: no contemporaneous tracking of actual costs and no review of the work cards that recorded what the mechanics did.
Quantities matter as much as hours. A unit rate needs a count of what was installed in the same weeks, from daily reports, progress payment applications or quantity surveys. Perini's progress was measured by the dollar value of work performed by the end of each year, which let the Board compute a daily rate for the baseline years.
The events need their own record: change orders, time extensions, correspondence and schedule updates that date the disruption. In Perini those were the 153 days of extensions under Modifications 10 and 11 and the 56-day reinforcement delay. In Trane the court noted that Lynn did not investigate whether the shift-work conditions described in OT2 existed on the project at all.
How does a court test a productivity expert under Rule 702?
The judge acts as gatekeeper. In Trane the court examined the expert's qualifications, the foundations of each opinion, relevance and helpfulness, and whether sufficient data and reliable methods were reliably applied to the project.
The Trane opinion describes trial judges as "gatekeepers" who keep speculative and unreliable opinions from the jury, and calls for an "exacting analysis" of the foundations of the opinion. The Daubert challenges had not been raised as timely motions, but the court wrote that it could not admit the opinions without vetting them, and it excluded Lynn's overtime and shift-work opinions.
Agri-Systems went the other way. By Bradley's account, the expert there had identified the differences between the two projects and explained them, and the remaining differences went to the weight of the testimony. In Trane the expert worked with payroll records and published tables. In Agri-Systems the expert worked with data from two projects and accounted for the differences between them.
Boards of contract appeals hear the experts and weigh the analyses themselves. In King Aerospace neither expert was excluded; the majority found one analysis unconvincing and adopted the other expert's bottom line, and the concurrence reached the same amount by a different route.
Which experts does a lost productivity claim need?
A productivity or cost expert who builds the comparison, a scheduling expert who ties the bad period to specific events, and a witness on site conditions. The opposing party needs the same specialties for rebuttal.
The cost expert chooses the baseline, checks the cost coding and computes unit rates for both periods. The same expert usually answers the alternative the other side offers, as Overman did in King Aerospace by accepting the method and contesting the years.
The scheduling expert dates the disruptive events and shows which activities they reached, which is the link Perini drew between the 1991 changes and the choice of baseline. In a footnote the Trane court called it circular to argue that the project was delayed by overtime inefficiency and that there was overtime inefficiency because there was a delay.
A project witness, such as a superintendent or foreman, describes crew sizes, overtime, shifts and access to the work. Lynn's failure to visit the site or ask about actual conditions was one of the reasons the Trane court gave for excluding him.
How does IAE find an expert for a lost productivity claim?
In the request choose the case type Construction and describe the project, the disruption, the periods compared and the forum. Within 5 business days IAE sends 2-3 candidates with CVs, hourly rates and lists of prior testimony.
The IAE page on construction expert witnesses lists 7 specialties: structural engineering, geotechnical engineering, architecture, building envelope, MEP systems, cost estimating and scheduling. On that page cost estimators price the scope the engineers define, scheduling experts analyze delay, and home office overhead for delay on a federal contract is computed with the Eichleay formula. The page notes that state courts apply their own rules on expert admissibility, so the request names the state and the court or the board.
The request form asks for the field of expertise, the case type, the state and court, the firm's side, the expert disclosure deadline, the parties and their counsel for the conflict check, and a short description of the case. The form asks not to include privileged or sealed information. Within 1 business day IAE replies whether it can search in that field by the deadline.
The search costs $2,000 per case, paid in advance, and candidate names and CVs come after payment. Each candidate confirms in writing that he or she has no ties to the parties or their counsel. The candidate materials include testimony in the last 4 years and publications in the last 10 years. If no candidate fits, the second search is free; if IAE finds no candidates, it refunds the fee. IAE is not a law firm: case strategy and the decision to retain an expert stay with the attorney.
Sources
- Appeal of King Aerospace, Inc., ASBCA No. 60933 (Apr. 15, 2019) (Armed Services Board of Contract Appeals)
- Appeal of Perini Corp., ASBCA No. 51573, decision on reconsideration (May 12, 2004) (Armed Services Board of Contract Appeals)
- Trane US Inc. v. Yearout Service, LLC, No. 5:17-cv-42, Document 184 (M.D. Ga. June 20, 2019) (Justia)
- Agri-Systems v. Structural Technologies, LLC, No. 1:19-cv-02238 (D. Colo.), docket (Justia Dockets)
- Court Allows Expert Testimony Regarding Measured Mile Analysis Comparing Work on Different Projects (Bradley, June 2023)
Read also
All articles
Spearin doctrine: when does the owner bear the cost of defective plans and specifications, and what does the contractor's expert have to prove?
Under the Spearin doctrine, an owner who gives the contractor plans and specifications impliedly warrants that work built to them will be adequate
Differing site conditions claim: what must the contractor prove, and which experts carry the proof?
A differing site conditions claim asks the owner to pay for ground the contract did not describe. On federal projects the clause is FAR 52.236-2
SB 800 construction defect claims in California: which standards apply, what comes before a lawsuit and what must the expert prove?
SB 800, enacted in 2002, governs construction defect claims against builders of new homes in California. Civil Code section 896 lists buildingExpert witnesses