Contract Disputes Act claim certification: what must the contractor certify, and where does the construction expert come in?

A contractor's claim against the federal government for more than $100,000 must be certified under 41 U.S.C. 7103(b): made in good faith, supported by accurate and complete data, stated in the amount the contractor believes is owed, signed by an authorized person. A defective certification can be corrected. A baseless one cost Daewoo a $50.6 million penalty, which the Federal Circuit affirmed in 2009. The cost and schedule work behind the claim is the data the certifier vouches for.

A contractor seen from behind signs a short form in a jobsite trailer beside a hard hat

When does a Contract Disputes Act claim have to be certified?

When a contractor's claim against the federal government exceeds $100,000. Every claim must be in writing and go to the contracting officer within 6 years after it accrues; above that amount it also needs the certification in section 7103(b).

Section 7103(a) of title 41 sets the basic rules for every contractor claim relating to a federal contract. Each claim is submitted to the contracting officer for a decision, and each claim must be in writing. Under section 7103(a)(4) the claim must be submitted within 6 years after it accrues, with an exception for certain government claims that involve contractor fraud.

The certification starts above $100,000. Section 7103(b)(1) applies to "claims of more than $100,000 made by a contractor", and FAR 33.207(a) repeats the threshold for any claim exceeding $100,000. FAR 33.207(d) states: "The aggregate amount of both increased and decreased costs shall be used in determining when the dollar thresholds requiring certification are met."

Two limits follow from the regulation. FAR 33.207(b) says the requirement "does not apply to issues in controversy that have not been submitted as all or part of a claim." For smaller claims the statute sets its own clock: under section 7103(f)(1) a contracting officer decides a claim of $100,000 or less within 60 days after the contractor asks in writing for a decision within that period.

What exactly must the certification say?

FAR 33.207(c) prescribes one text: good faith, accurate and complete supporting data, an amount that states the adjustment the contractor believes the government owes, and authority to certify for the contractor.

The regulation gives the words, and the certifier signs them in the first person. The text opens with "I certify that the claim is made in good faith" and continues "that the supporting data are accurate and complete to the best of my knowledge and belief". The third clause ties the amount requested to the contract adjustment for which the contractor believes the Government is liable. The last clause reads "and that I am duly authorized to certify the claim on behalf of the contractor."

Section 7103(b)(1) of the statute lists the same four elements in subparagraphs (A) through (D). The first is a statement about honesty, the second about the data, the third about the number and the fourth about the signer.

The cases below turned on the last two. In one the signer used certification language taken from a different form. In the other the contractor certified an amount that the trial court found it did not believe it was owed. Both cases started with the same document: a signed certification attached to a claim.

Who may sign the certification?

A person authorized to bind the contractor with respect to the claim. Section 7103(b)(2) and FAR 33.207(e) tie the signature to authority over the claim, not to a job title or a technical role.

Section 7103(b)(2) provides that the certification may be executed by an individual authorized to bind the contractor with respect to the claim. FAR 33.207(e) says any person so authorized may execute it. A project director or a claims manager can sign if the company has given that person authority over the claim.

A cost consultant or a scheduling expert who prepared the numbers signs the expert report on those numbers. The certification is a different document: it is the contractor's statement about the whole claim, including the data the consultant supplied. The certifier states that the supporting data are accurate and complete to the best of his or her knowledge and belief, so the certifier has to know what those data are, who prepared them and what they assume.

What happens if the certification is defective?

The claim stays alive. A defect does not take away the jurisdiction of a court or a board, but it must be corrected before final judgment or decision, and the contracting officer has 60 days to point it out.

Section 7103(b)(3) gives the contracting officer a choice. The officer need not issue a decision on a claim of more than $100,000 that is not certified if, within 60 days after receiving the claim, the officer explains to the contractor in writing why the attempted certification is defective. The same paragraph says that a defect in the certification "does not deprive a court or an agency board of jurisdiction over the claim". Before a court enters final judgment or a board decides, it must require the defective certification to be corrected. FAR 33.207(f) repeats the rule on jurisdiction and correction.

The Federal Circuit applied this text on December 27, 2019 in DAI Global, LLC v. Administrator of the United States Agency for International Development (No. 2019-1330). DAI held five USAID contracts in Afghanistan and passed on claims of its security subcontractor after Afghanistan fined that subcontractor nearly $2 million on April 1, 2011. On May 10, 2017 DAI sent the claims with a cover letter that described itself as a certification. On July 19, 2017, 70 days after submission, the contracting officer told DAI that the contractor certification was missing. The Civilian Board of Contract Appeals dismissed the appeals for lack of jurisdiction: it found that the letter bore no resemblance to the statutory language and that DAI had acted with reckless disregard of the requirements.

The Federal Circuit reversed. It held that section 7103(b)(3) "does not limit defects to those that are technical in nature" and does not bar correction because the contractor disregarded the requirements intentionally, recklessly or negligently. DAI's submission was a defective certification. Because the contracting officer had not given notice within 60 days, the claims were deemed denied and DAI could appeal to the board.

How did the ASBCA treat a certification copied from the wrong form?

In ASBCA No. 62980, decided on March 24, 2025, the Armed Services Board of Contract Appeals kept a $13.7 million claim whose only certification language came from the DFARS form for requests for equitable adjustment.

The contractor, called KP in the decision, built a facility for the U.S. Strategic Command under an Army Corps of Engineers contract awarded on August 16, 2012. On July 10, 2020 it sent a serial letter asking for a final decision on a two-part claim of $13,702,363: $8,803,026 for delay and disruption and $4,899,337 for costs tied to an earlier claim. The project director signed the letter, which contained no certification language. The attached proposed change orders carried the DFARS 252.243-7002 certification and named the project director, but their signature blocks were blank.

On September 29, 2020, after a request from a DCAA auditor, the contractor gave DCAA a signed certification; it never reached the contracting officer. The final decision of April 16, 2021 said the claim was not properly certified, reviewed the merits anyway and found partial merit. The contractor appealed on July 9, 2021.

Administrative Judge Laura Eyester denied the government's motion to dismiss in ASBCA No. 62980. She found the project director's signature sufficiently linked to the certification language in the attachments, so a certification had been provided. It was defective because it was the DFARS certification for a request for equitable adjustment and not the CDA wording. As an alternative ground, the Board found the defect cured by the signed DCAA submission, which the contracting officer knew about. The decision says the question "may be a close call," and a footnote calls the failure to sign at the certification location "a poor practice, not to be emulated."

What happens when the certified amount has no basis?

The contractor can lose the claim and owe money. Section 7103(c)(2) makes it liable for any unsupported part of the claim caused by its misrepresentation of fact or fraud, plus the government's cost of reviewing that part.

Under section 7103(c)(2), a contractor that cannot support part of its claim because of its own misrepresentation of fact or fraud owes the government an amount equal to the unsupported part plus the government's costs of reviewing it. Liability must be determined within 6 years after the misrepresentation or fraud.

The Federal Circuit applied the predecessor provision, then 41 U.S.C. 604, in Daewoo Engineering & Construction Co. v. United States, decided on February 20, 2009 (No. 2007-5129). Daewoo held an Army Corps of Engineers contract, awarded on March 30, 1999 for $88.6 million, to build a 53-mile road around Babeldaob Island in the Republic of Palau within 1,080 days. On March 29, 2002 it submitted a certified claim of about $64 million: $13,348,793.07 in costs through December 31, 2001 and $50,629,855.88 in costs projected for the period after January 1, 2002.

The Court of Federal Claims found that the projection assumed every day past the original completion date was the government's responsibility. It found that the claim was simply a "negotiating ploy" and that Daewoo "did not honestly believe that the Government owed it the various amounts stated when it certified the claim." It imposed a penalty of $50,629,855.88 under the CDA fraud provision and a $10,000 penalty under the False Claims Act, and held Daewoo's own claims forfeited under 28 U.S.C. 2514.

The Federal Circuit affirmed. Daewoo argued that only false facts, and not baseless calculations, can make a claim fraudulent; the court rejected that argument and wrote that "a baseless certified claim is a fraudulent claim." It also held that the $50.6 million penalty did not violate the Eighth Amendment.

Where does the construction expert fit into a certified claim?

Behind the supporting data. Cost estimators and scheduling experts build the quantum and delay analysis that the certifier calls accurate and complete, and the same work is later tested as expert evidence.

The certification covers the supporting data as well as the amount. In a delay or changes claim those data are the cost records, the estimate of the changed work and the schedule analysis that assigns each period of delay to a cause. Daewoo's projection failed on that last point: it charged every day of overrun to the government.

After the contracting officer's decision the dispute can go to a board or to the Court of Federal Claims. Under section 7104(b)(4) an action in the Court of Federal Claims proceeds de novo under the rules of that court, so the contractor proves the claim with the evidence offered there. Section 7103(e) adds that specific findings of fact in the contracting officer's decision are not binding in later proceedings.

Where the Federal Rules of Civil Procedure govern expert discovery, Rule 26(a)(2)(B) requires a retained expert's written report to state all opinions with their basis and reasons, the facts or data considered, the exhibits, the expert's qualifications with publications from the previous 10 years, the cases in which the expert testified in the previous 4 years and the compensation. Under Rule 702 of the Federal Rules of Evidence, as amended on December 1, 2023, the party offering the expert must show the court that it is more likely than not that the opinion rests on sufficient facts or data and on a reliable application of reliable methods.

What happens after the contracting officer decides, or fails to decide?

The contractor has 90 days to appeal to an agency board or 12 months to sue in the Court of Federal Claims. A decision that does not come within the required period counts as a denial that can be appealed.

For a certified claim over $100,000, section 7103(f)(2) requires the contracting officer, within 60 days after receiving it, either to issue a decision or to tell the contractor when a decision will be issued. Under section 7103(f)(3) the decision must come within a reasonable time, in view of the size and complexity of the claim and the adequacy of the supporting information. If the officer delays unduly, the contractor may ask the tribunal to direct a decision within a set period (section 7103(f)(4)). A failure to decide within the required period is deemed a decision denying the claim (section 7103(f)(5)).

The decision must be in writing, state its reasons and tell the contractor of its rights (section 7103(d) and (e)). Under section 7103(g) it is final and conclusive and not subject to review in any forum unless an appeal or action is filed on time. Section 7104(a) gives the contractor 90 days after receiving the decision to appeal to an agency board, and section 7104(b)(3) gives 12 months to bring an action in the Court of Federal Claims instead.

How does IAE find an expert for a federal construction claim?

Choose the case type Construction and describe the contract, the agency, the forum and the question, such as delay or cost. Within 5 business days IAE sends 2-3 candidates with CVs, hourly rates and testimony lists.

The IAE page on construction expert witnesses lists 7 specialties: structural engineering, geotechnical engineering, architecture, building envelope, MEP systems, cost estimating and scheduling. On that page cost estimators price the repair scope the engineers define, scheduling experts analyze delay, and home office overhead for delay on a federal contract is computed with the Eichleay formula.

The request asks for the field, the case type, the court, the firm's side and the expert disclosure deadline, and for the parties and their counsel for the conflict check. Privileged or sealed information stays out of the request. Within 1 business day IAE replies whether it can search in that field by the deadline. The search costs $2,000 per case, paid in advance, and candidate names and CVs come after payment.

Each candidate confirms in writing that he or she has no ties to the parties or their counsel. The candidate materials include testimony in the last 4 years and publications in the last 10 years, the lists that Rule 26(a)(2)(B) requires. If none of the candidates fits, the second search is free; if no candidates are found, the fee is refunded. IAE is not a law firm: the certification, the claim strategy and the decision to retain an expert stay with the contractor and its attorney.

Sources

Read also

All articles

Expert witnesses

Need an expert witness for your case?

Describe the question, the case type and the court. Within 5 business days you receive 2-3 candidates with CVs, hourly rates and lists of prior testimony.

Expert request

Received

Candidates, rates and prior testimony within 5 business days

Candidates2-3 with CVs
Timeline5 business days
Search$2,000 per case