Florida construction defect statute of repose: when does the 7-year period start, and what can still be filed?
In Florida an action founded on the design, planning or construction of an improvement to real property must be commenced within 7 years after the earliest certificate or abandonment of the work, even if nobody has found the defect. That is section 95.11(3)(b) after SB 360 of 2023, which cut the period from 10 years. A chapter 558 notice does not stop this clock. The defect expert pins down the dates.

What is Florida's statute of repose for construction defect claims?
A 7-year outer limit in section 95.11(3)(b) for actions founded on the design, planning or construction of an improvement to real property, counted from the earliest certificate or abandonment, regardless of when the defect is discovered.
Section 95.11 of the Florida Statutes lists limitation periods by type of action. In the 2026 statutes the paragraph on construction is 95.11(3)(b). It covers an action "founded on the design, planning, or construction of an improvement to real property" and sets two periods: 4 years, with a discovery rule for latent defects, and an outer limit of 7 years that runs regardless of discovery.
The start date is the same for both. The time runs from the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy or a certificate of completion, or from the date of abandonment if construction is not completed, whichever date is earliest.
Section 95.011 defines "action" for the chapter as a civil action or proceeding, including actions brought by the state, public officers, political subdivisions and other governmental bodies. The repose period applies to claims against contractors, subcontractors and design professionals alike, because the paragraph turns on what the claim is founded on: design, planning or construction.
What did the 2023 law change?
SB 360 of 2023 shortened the outer limit to 7 years, down from 10, made the earliest triggering date control instead of the latest, and dropped owner possession and contract completion as starting points.
The enrolled text of CS/SB 360 shows the amended paragraph, then numbered 95.11(3)(c), with old and new words side by side: "7 10 years" and "earliest latest". The old version counted from the latest of several events, among them the date of actual possession by the owner and the completion or termination of the contract. The 2026 statute counts only from the certificates or abandonment, and the earliest of those dates controls.
The change matters most for long projects. Under the old rule the latest event controlled, so a contract completed long after the certificate of occupancy pushed the start of the period forward. Under the current text the clock starts with the first certificate the building department issues, even if work under the contract continues after that date.
The current paragraph keeps three special rules. For construction performed under a duly issued building permit with a certificate of occupancy or completion, correcting or repairing completed work, whether under warranty or otherwise, does not extend the period. For a newly built single-dwelling residential building used as a model home, the time starts when a deed first transferring title to another party is recorded. When a project has several buildings, each building is its own improvement for the limitation period.
Which claims fell under the new 7-year rule, and what was the July 1, 2024 deadline?
The amendments apply to any action commenced after the act took effect, whenever the claim accrued. Actions that the old rule allowed but the new rule bars had to be filed by July 1, 2024.
Section 3 of SB 360 says the amendments to section 95.11(3)(c) "apply to any action commenced on or after the effective date of this act, regardless of when the cause of action accrued." Section 4 provides that the act takes effect upon becoming a law.
The same section gives a grace period: "any action that would not have been barred under s. 95.11(3)(c), Florida Statutes, before the amendments made by this act must be commenced on or before July 1, 2024." If such an action was not commenced by that date and is barred by the amendments, it is barred.
For a building completed in 2017, for example, the old 10-year period would have run to 2027, while 7 years from a 2017 certificate ended in 2024. An owner in that position had until July 1, 2024 to sue. A claim on that building filed in 2026 is measured by the 7-year rule.
How does the 4-year limitation period differ from the 7-year repose?
Both start on the same earliest date. For a latent defect the 4 years run from discovery, or from when the defect should have been discovered with due diligence, but the action must still be commenced within 7 years.
The 4-year limitation period and the 7-year repose period start on the same earliest date. When the action involves a latent defect, section 95.11(3)(b) moves the start of the 4-year period: the time runs from when the defect is discovered or should have been discovered with the exercise of due diligence.
The repose period has no discovery rule. The statute says that in any event the action must be commenced within 7 years after the earliest date. A defect found in year 6 leaves the owner about one year to file. A defect found in year 8 cannot support an action founded on the construction, whatever its cause.
The two periods put different facts in play. For limitations the question is when the owner knew or should have known of the defect, which turns on what was visible and when. For repose the question is when the certificate issued or the work was abandoned, which turns on public records.
Which document starts the clock, and how is the date proved?
The earliest temporary certificate of occupancy, certificate of occupancy or certificate of completion issued by the authority having jurisdiction, or the date of abandonment. Building department records prove the certificate dates.
The statute names the documents, so the proof starts with the permit file of the authority having jurisdiction: the permit, inspection results, and the temporary certificate of occupancy, certificate of occupancy or certificate of completion with its date. Where a temporary certificate came first, that earlier date controls.
For a project with several buildings, each building has its own date. A defect claim that covers a whole complex is therefore several claims for repose purposes, and the defect expert's findings have to be tied to specific buildings. An expert report that lists defects by building lets the parties apply the right date to each item.
Abandonment is the fallback where construction was not completed. Its date is a fact question that turns on the record of the job: the last work performed, the last inspection, correspondence about stopping work. Model homes have a separate start, the recording of the first deed that transfers title to another party.
Warranty work does not move the date. Under the current paragraph, for construction under a duly issued permit with a certificate of occupancy or completion, correcting or repairing completed work does not extend the period, whether performed under warranty or otherwise.
Does a chapter 558 notice stop the repose clock?
No. Section 558.004(1)(d) states that a notice of claim served under chapter 558 "shall not toll any statute of repose period under chapter 95." The notice tolls only the statute of limitations, for a limited time.
Before suing on a construction defect in Florida, the claimant serves a notice of claim under chapter 558. In the 2025 Florida Statutes, section 558.004(1)(d) reads: "A notice of claim served pursuant to this chapter shall not toll any statute of repose period under chapter 95." The history line of section 558.004 lists, among other amendments, section 8 of chapter 2019-75.
The statute of limitations is treated differently. Under section 558.004(10), service of the notice tolls the applicable statute of limitations for any person covered by the chapter until the later of 90 days, or 120 days where that period applies, after service of the notice, or 30 days after the end of the repair or payment period stated in an accepted offer. The parties may extend the period by stipulation, and the statute of limitations is tolled during the extension.
Section 558.002(1) defines "action" for chapter 558 as any civil action or arbitration proceeding for damages or indemnity. The chapter 558 process takes weeks or months, so a claimant who serves the notice close to the end of the 7-year period can lose the claim while the parties inspect and negotiate.
What did the court decide in Gindel v. Centex Homes?
It held that serving the chapter 558 notice counted as commencing an action for repose purposes. The homeowners took possession in 2004, served the notice in February 2014 and sued in May 2014, after the old 10-year period.
In Gindel v. Centex Homes, reported at 267 So. 3d 403, the homeowners took possession of their townhomes on March 31, 2004, which started the 10-year period under the statute then in force. On February 6, 2014 they served a chapter 558 notice of defect on Centex, which later said it would not cure. They filed suit on May 2, 2014. The trial court held that the action commenced when suit was filed, after the repose period, and granted summary judgment for Centex.
The appellate court reversed. It agreed with the homeowners "that Chapter 558 lays out a series of mandatory steps" and held that compliance with the pre-suit notice requirement constitutes an "action" for purposes of the statute of repose. It wrote that "Chapter 558 was not intended as a stalling device in order to bar claims" and that "Homeowners should not be penalized for rightly complying with the mandates of the statute."
Gindel was decided under the earlier texts of sections 95.11 and 558.004. A claimant today reads section 558.004(1)(d) in its 2025 text, which says that the notice does not toll the repose period, and counts 7 years from the earliest certificate rather than 10 years from possession.
Can a defendant still bring claims against subcontractors after the repose period?
For a limited time. Under section 95.11(3)(b), counterclaims and third-party claims may be commenced up to 1 year after service of the pleading to which they relate, even if they would otherwise be barred.
A general contractor sued in year 7 may want to bring in the subcontractors whose work is at issue. The current paragraph permits a counterclaim, cross-claim or third-party claim to be commenced up to 1 year after the pleading to which it relates is served, even if that claim would otherwise be time-barred.
That year starts with service of the owner's pleading, so the contractor's own expert needs to sort the alleged defects by trade early. The third-party complaint has to name who built what, and that comes from the same building-by-building findings the repose defense uses.
What does the defect expert need to establish when repose or limitations is raised?
The building, the dates and the visible history of each defect: which certificate applies, when signs of the defect first appeared, whether the defect lies in the original construction or in later repairs, and which trade built it.
For the 7-year repose the expert's work is mostly records: the permit file, the certificate dates for each building, and a schedule that ties each alleged defect to a building and an element. A defect map by building lets the court apply the earliest certificate date to the right items.
For the 4-year limitation period on a latent defect the expert addresses discovery: when cracks, stains, leaks or other signs became visible, what earlier inspection reports and maintenance records show, and whether a reasonable owner would have noticed. Evidence of this kind includes dated photographs, association minutes and repair invoices. Repairs done under warranty do not restart the period, so the expert separates the original work from later corrective work in the report.
In court the expert's opinions are tested like any other expert evidence. In federal court Rule 702 of the Federal Rules of Evidence, as amended on December 1, 2023, requires the party offering the expert to show that it is more likely than not that the opinion rests on sufficient facts or data and a reliable application of reliable methods.
How does IAE find a construction expert for a Florida repose dispute?
Choose the case type Construction and describe the building, the county, the certificate dates if known and the question. Within 5 business days IAE sends 2-3 candidates with CVs, hourly rates and testimony lists.
The IAE page on construction expert witnesses lists 7 specialties: structural engineering, geotechnical engineering, architecture, building envelope, MEP systems, cost estimating and scheduling. It covers Florida condominium milestone inspections under section 553.899 and summarizes what a notice of construction defect must contain under section 558.004.
The request asks for the field, the case type, the court, the firm's side and the expert disclosure deadline, and for the parties and their counsel for the conflict check. Privileged or sealed information stays out of the request. Within 1 business day IAE replies whether it can search in that field by the deadline. The search costs $2,000 per case, paid in advance, and candidate names and CVs come after payment.
Each candidate confirms in writing that he or she has no ties to the parties or their counsel, and the candidate materials include testimony in the last 4 years and publications in the last 10 years. If none of the candidates fits, the second search is free. IAE is not a law firm: whether a claim is barred, and when to serve a notice or file suit, are questions for the attorney.
Sources
- Florida Statutes 2026, chapter 95, Limitations of actions, sections 95.011 and 95.11 (Florida Senate)
- CS/SB 360 (2023), enrolled bill text, Causes of action based on improvements to real property (Florida Senate)
- Florida Statutes 2025, chapter 558, Construction defects, sections 558.002 and 558.004 (Florida Senate)
- Gindel v. Centex Homes, 267 So. 3d 403, opinion text (Caselaw Access Project)
- Federal Rules of Evidence, Rule 702, with committee notes (uscode.house.gov)
Read also
All articles
Spearin doctrine: when does the owner bear the cost of defective plans and specifications, and what does the contractor's expert have to prove?
Under the Spearin doctrine, an owner who gives the contractor plans and specifications impliedly warrants that work built to them will be adequate
Differing site conditions claim: what must the contractor prove, and which experts carry the proof?
A differing site conditions claim asks the owner to pay for ground the contract did not describe. On federal projects the clause is FAR 52.236-2
SB 800 construction defect claims in California: which standards apply, what comes before a lawsuit and what must the expert prove?
SB 800, enacted in 2002, governs construction defect claims against builders of new homes in California. Civil Code section 896 lists buildingExpert witnesses